Forms and Process

Generate PO From Project

image-1695203847599.png

Parameter :- 

1.Project : a series of tasks that must be accomplished in order to achieve a specific result, including phases and phase lines as sequential tasks to complete a project. It is master data.
2.Project Phase : Phase lines are  series of duties to complete a project which contains activities, task and task lines.
3.Project Line : Project lines are successive steps to be followed. 


Process :-

This Process is used to Generate Purchase order from project master

Issue to Project

image-1698646795383.png

Parameter :- 

1. Project : Project is to be selected for which user wants to issue material
2. Shipment/Receipt : The project-related shipment/receipt document to be selected.
3. Expense Report : To select Expenses report in-relation with project 
4. Locator : Locator to be selected accordingly or it will be auto-fetched
5. Project Line : Project line details for which user wants to issue material
6. Product : Product is be selected. 
7. Attribute Set instance : Attribute set applied to product is product master is to be selected.
8. Movement Quantity : Quantity required
9. Movement Date : Date of material movement
10 .Description : Any specifics or information.

Process :-

This process is used to Issue Material to Project from Receipt or manual Inventory Location