Document Action
Validations
Save:
1) System will check whether all the Mandatory Fields are filled.
2) System will check the vendor,vendor location
Delete:
System will delete the order and its history from the database.This can be done only when the document status is Draft status and In progress Status.
Document action prepare:
1) System will check the vendor,vendor location and convert the document status to In progress.
2) System will check the Period control for the document date whether it is open.
Document action complete:
System will complete the document and change the document status to complete.
Document action void/reverse correct actual:
Document action close:
1) System will check whether all the issued material is returned and the delivered check box is check and change the Document status to close.
Actions
Verify:
Not applicable
Create lines from:
User can select the received components list by selecting Subcontract issue document number or Purchase order document (Tagged in Subcontract Issue Header).by selecting the refresh button system will display the components from the selected criteria.Select the components received and enter the quantity received and click Ok.
Copy from/lines:
Not applicable
<custom actions>
Not applicable