Action (Forms)

Ok

1) System will start or stop the selected operation.

2) While starting the operation system will create a Activity control document with the required field updated and keep the document in In progress status.

3) While stopping the operation system will update the movement quantity in the Activity control Report and Complete document.

4) After The stop operation is completed the operation will be taken out from the Production Que.

Close

 

Display

System will display the records for as per the selection criteria.

a) If manufacturing order is selected system will verify the manufacturing order document number and operation which are not completed will be displayed.

b) If work center is selected system will verify the all the manufacturing order which are ready to process with the resource selected and display the records.

c) If Resource group is selected system will verify the all the manufacturing order which are ready to process with the resource group and display the records.

Zoom/details

 

Delete

 

Add

 

Refresh

Refresh or Re-query - If no selection is provided using this button system will display the records of operation which are ready to process.

Reset

System will reset the selection criteria's.Back to Empty.

<Custom Buttons>

1) Start Operation- While clicking this button system allows you to select operator name and Quantity that need to be produced.

2) Stop Operation - Allowing the System to Enter the End Quantity that need to be processed.

3) Change Resource- System allows to change the resource which is allocated for the operation.

4) Show PR- If the operation is subcontract once the operation is started,System will generate a requisition document.By selecting the operation and clicking this button system will Zoom into the Requisition created for that operation.

5) Download- This button download the datas from the production Que screen as per selection criteria to an Excel Sheet.